    济南化粪池清理流程
    2013-12-25 17:01:18   http://www.jnhualu.net

    化粪池清理施工程序

    Septic tank cleaning construction program

    一、济南化粪池作业前工作准备

    One, job preparation before

    1、制订合理的工作安排和合理的工期。

    1, formulate a reasonable working arrangements and reasonable period.

    2、检查安全防护工具,检查设备,检查车辆工作能力,水电是否可供应。

    2, check the safety protection tools, inspection equipment, work ability inspection of vehicles, whether can supply power.

    3、将准备施工的化粪池提前2-4小时打开用轴流风机进行通风。

    3, the preparation for construction of the septic tank 2-4 hours in advance to open for ventilation of axial flow fan.

    二、济南化粪池正式施工

    Two, the formal construction

    1、施工前应明确清理标准:水面无漂浮物,池壁基本清洁,作业现场基本卫生保障。

    1, before the construction should be clear: no standard water floating objects, the pool wall basic cleaning, operation site basic health security.

    2、仪器检查化粪池内是否有毒气,在没有毒气的情况下组织车辆抽运化粪池内的漂浮物。

    If there is gas 2, instrument check the septic tank, in the absence of gas of the organization vehicle pumping floating septic tank.

    3、二次处理利用高压清洗车把沉淀的粪便及污泥稀释,把隐藏在化粪池底层的毒气排放出来,然后将化粪池内的污水排干,仪器再次检测池内是否有毒气。

    3, two times the use of manure and sewage sludge of high pressure cleaning handlebar precipitation dilution, hidden in the bottom of the gas emitted from the septic tank, and then the septic tank sewage drained, instrument again detect gas pool.

    4、作业人员系安全带、消防软梯、配带长管呼吸器下井作业。

    4, operation personnel safety belt, fire ladder, with long tube respirators downhole operation.

    5、将化粪池下面的沉淀物打包处理,利用电动升将设备升井,然后放入密封推车外运(这样可保证施工现场和外运路段的卫生问题)。

    5, the septic tank below the sediment package processing, using electric lifting equipment or wells, and then sealed carriage Sinotrans (which can ensure the health of the construction site and Sinotrans road).

    6、作业人员下井作业必须2小时更换一次(循环作业)。

    6, operation personnel downhole operation must be replaced every 2 hours (cycle).

    7、施工后应明确的外运要求:做到每天产生的垃圾进行装袋,运离施工现场,进行消纳。

    7, the construction should be clear Sinotrans requirements: do daily garbage generated by bagging, transported from the construction site, for consumption.

    济南化粪池  http://www.jnhualu.net/